Non-negligent liability insurance
Construction is an inherently dangerous process with many hazards, in particular when working close to existing buildings or other structures. In such situations, there is the potential for that property to suffer damage, even if care is exercised.
As a result of the potential for these sorts of losses to occur on construction projects, Joint Contracts Tribunal (JCT) contract forms provide for non-negligent liability insurance to be taken out, and other forms of contract may have similar provisions, either as part of the standard form or as an amendment.
Such provisions require that the contractor takes out a policy that protects the developer in respect of any expense, liability, loss, claim or proceedings incurred as a result of damage to property from the works being undertaken due to; collapse, subsidence, heave, vibration, weakening or removal of support and lowering of ground water. It is also possible to include cover from the hazards of flood, explosion, backing up of drains and bodily injury to third parties caused by an insured peril.
The cover may be in respect of existing buildings being worked upon and/or property on adjoining land. The policy is issued in the joint names of the employer and contractor.
This sort of cover is not always be required as the kind of activities which give rise to such losses may not be present on all projects. Consultants will usually be able to recommend whether or not the cover is required.
There are a variety of activities that could give rise to the potential hazards covered by the insurance, including:
- Piling and foundation excavations
- Underpining.
- De-watering of the ground
- Demolition close to an existing property.
- Shoring of walls
- Works that may affect the load-bearing capacity of a structure.
- Works on listed buildings or buildings in a poor condition.
Typical exclusions from non-negligent cover might include:
- Damage caused by negligence, omission or by default of the contractor or subcontractor.
- Damage which is due to error or omissions during the design process.
- Damage which could reasonably have been foreseen as inevitable.
- Penalties incurred under contract and damages for breach of contract.
The Royal Institute for Chartered Surveyors (RICS) have produced a guidance note which provides further information on non-negligent liability insurance, including details of Gold v Patman & Fotheringham (1958), the landmark case in this situation.
[edit] Related articles on Designing Buildings Wiki.
- 3D animation for insurance risk analysis.
- Building Users' Insurance Against Latent Defects.
- Contractors' all-risk insurance.
- Contract works insurance.
- Directors and officers insurance.
- Employer's liability insurance.
- Flood insurance.
- Insurance.
- Insurance terminology.
- Integrated project insurance.
- Latent defects insurance.
- Legal indemnity insurance.
- Professional Indemnity Insurance.
- Public liability insurance.
- Residual value insurance.
[edit] External references
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.